Keighley & Stockbridge flood scheme business case work goes to Arup
- Environment Agency
- Yorkshire and the Humber
- Call-off from a framework agreement
- 16 March 2026 to 7 January 2028
The Environment Agency has appointed Arup to take the Keighley & Stockbridge flood alleviation scheme from outline business case to full business case. The full business case is what the scheme needs for final approval and the move into construction. Arup's work covers design development, project management and technical advice.
The £880,000 professional services contract was called off from a framework agreement. It runs from March 2026 to January 2028.
Contract ends January 2028
- What
- Flood risk, drainage and coastal engineering
- Buyer
- Environment Agency
- Supplier
- Arup
- Value
- £880,000
- How it was bought
- Call-off from a framework agreement
- Dates and next