North East flood asset works at four sites go to Cheetham Hill Construction
- Environment Agency
- North East
- Call-off
- 1 May 2026 to 30 March 2027
The Environment Agency ordered flood defence works at four North East sites from Cheetham Hill Construction Limited, through its Asset Operation, Maintenance and Response Framework. The package covers Willows Embankment, Loftus Walls, Trafford Hill Culvert and Bellingham Embankments. It sits within the agency's North East Area Asset Recon Programme 26 to 27.
The order came under Lot 1 of the framework, which covers civil engineering maintenance and construction. The work is worth £946,499. It started in May 2026 and is due to finish in March 2027.
Contract ends March 2027
- What
- Flood defence and flood alleviation works
- Buyer
- Environment Agency
- Value
- £946,499
- How it was bought
- Call-off, Asset Operation, Maintenance and Response Framework
- Dates and next
- May 2026 to Mar 2027