Eastern Revetment Sloping Wall at Rye Harbour is repaired by VolkerStevin
- Environment Agency
- South East
- Call-off from a framework agreement
- 3 August 2026 to 6 December 2027
The Environment Agency hired VolkerStevin to repair the Eastern Revetment Sloping Wall at Rye Harbour.
The repaired section has to line up with the rest of the revetment, with its southern end tied into the concrete quay wall. Site work and demobilisation are due to finish by 11 August 2027. Storm surges or high river flows that keep the tide above working level count as compensation events. So do wind gusts above 9.8 m/s that stop crane lifts.
The agency ordered the work under the Collaborative Delivery Framework. The £4,059,139 contract runs from August 2026 to December 2027.