Skinningrove flood defence works go to BAM Nuttall
- Environment Agency
- North East
- Call-off from a framework agreement
- 12 August 2026 to 6 October 2027
BAM Nuttall is building the Skinningrove flood defence scheme for the Environment Agency. The contract covers the construction stage of the scheme, which the agency placed as a call-off from a framework agreement.
BAM Nuttall was awarded the £7,155,986 contract in August 2026. The works run for 14 months and are due to finish in October 2027.
Contract ends October 2027
- What
- Flood defence and flood alleviation works
- Buyer
- Environment Agency
- Supplier
- BAM Nuttall
- Value
- £7.16m
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Aug 2026 to Oct 2027