The Environment Agency hired Arup to appraise the Tidal Ouse Left Bank Saltmarshe flood defence scheme.
Arup is writing the scheme's Strategic Outline Case (SOC) and Outline Business Case (OBC). The work pairs technical assessment with the business cases needed to support future investment in the flood defences and their upkeep.
The agency ordered the work from Arup as a call-off from a framework. The £241,911 contract runs from May 2026 to September 2027.