Tollesbury embankment repairs for the Environment Agency go to JBA Bentley
- Environment Agency
- East of England
- Call-off
- 26 May 2026 to 5 December 2026
JBA Bentley Ltd is repairing the embankment at Tollesbury for the Environment Agency.
The embankment is a coastal flood defence, and the civil engineering work is meant to keep its structure sound. The agency ordered the repairs through its Asset Operation, Maintenance and Response Framework.
The £79,921 contract started in May 2026 and is due to end in December 2026.
Contract ends December 2026
- What
- Flood defence and flood alleviation works
- Buyer
- Environment Agency
- Supplier
- JBA Bentley Ltd
- Value
- £79,921
- How it was bought
- Call-off, Asset Operation, Maintenance and Response Framework
- Dates and next
- May 2026 to Dec 2026