Class 387 LED lights for First Greater Western come from Craig & Derricott
- First Greater Western Limited
- South West
- Competitive flexible procedure
- 1 August 2026 to 28 February 2028
First Greater Western Limited bought LED lighting for its Class 387 train fleet from Craig & Derricott for £180,000, less than half its £450,000 estimate.
The contract is for supply only, because First Greater Western's own engineers fit the lights at the depot. Deliveries come every six months, each carrying enough lighting for 14 four-car vehicles. Over 18 months that covers 42 four-car vehicles in all. Each product has to comply with current rail passenger vehicle standards.
Quality counted for 55% of the score, price 40% and terms and conditions 5%. The supplier was chosen in June 2026, and the contract runs to February 2028.
Contract ends February 2028
- What
- Rolling stock maintenance, overhaul and spares
- Supplier
- Craig & Derricott Limited
- Value
- £180,000
- How it was bought
- Competitive flexible procedure
- Dates and next
- Aug 2026 to Feb 2028