Sherwood Office heat pumps for Forestry England installed by Ipsum Group
- Forestry England
- East Midlands
- 5 January 2026 to 23 January 2026
Forestry England hired Ipsum Group to fit air source heat pumps at its Sherwood Office.
The job centred on three single-phase Ecoforest ecoAIR+ 3-18 PRO heat pumps. Ipsum altered the pipework in all three heating zones and wired the system back to the main distribution board to balance the load. Three Cordivari PUFFER 200 stainless steel buffer cylinders and three thermostats went in too. The work followed specifications from Mesh Energy.
The £47,990 job was due to be finished in January 2026.
- What
- Heat pumps
- Buyer
- Forestry England
- Supplier
- Ipsum Group
- Value
- £47,990
- How it was bought
- Not published
- Dates and next
- Jan 2026 to Jan 2026