Gateshead Council chose Adler & Allan Limited to upgrade three pumping stations at Gateshead International Stadium. The contractor is to carry out the detailed design and the building work for all three, then keep them maintained afterwards.
The council ordered the work through its DPS For Construction Contractors and Sub-Contractors, and two bids came in. Quality and price each carried 40% of the score and social value 20%. The award was £232,257.
- What
- Pumping stations and small treatment plants
- Buyer
- Gateshead Council
- Supplier
- Adler & Allan Limited
- Value
- £232,257
- How it was bought
- Call-off, Gateshead Council
- 2 bids
- Dates and next
- 8 Dec 2025