Contract awardedDemolition and soft strip
Gateshead viaduct demolition is awarded directly to BAM Nuttall
- Gateshead Council
- North East
- 31 March 2025 to 30 September 2026
Gateshead Council hired BAM Nuttall to demolish the Viaduct in Gateshead. The council gave the job directly to BAM Nuttall, with no tender, and the contractor was to carry it out over 18 months.
The demolition contract was worth £20m. Work ran from March 2025 and was due to finish in September 2026.
- What
- Demolition and soft strip
- Buyer
- Gateshead Council
- Supplier
- BAM Nuttall
- Value
- £20m
- How it was bought
- Not published
- Dates and next
- Mar 2025 to Sep 2026