TDC feasibility and cost support for Greater Manchester goes to Constellia
- Greater Manchester Combined Authority
- North West
- Call-off from a framework agreement
- 1 March 2026 to 31 October 2027
Greater Manchester Combined Authority hired Constellia as client-side project manager and quantity surveyor for a refreshed TDC facility. The facility is meant to meet GMFRS's long-term estate needs.
GMCA ordered the work through a framework at £77,481. The contract runs from March 2026 to October 2027. The award notice appeared 167 days after the award.
Contract ends October 2027
- What
- Construction project management
- Supplier
- Constellia
- Value
- £77,481
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Mar 2026 to Oct 2027