Hydraulic and pneumatic components for GWR's fleet come from Tidyco
- First Greater Western Limited
- Direct award
- 1 December 2026 to 30 November 2027
First Greater Western Limited has hired Tidyco Limited to supply, repair and overhaul hydraulic and pneumatic parts for GWR's trains and depot equipment.
Valves, pumps, cylinders and seals are among the parts covered. Tidyco will also find faults, collect and return items, and test and certify them, with specialist engineering help when needed.
The £700,000 contract was awarded directly in September 2026 to give GWR time to run a full competitive tender for the longer term. It will run for a year, with an option of a second year that would take it to November 2028. GWR's services are due to move to a new public sector operator, ultimately owned by the Secretary of State for Transport. The contract may move with them.
Contract ends November 2027
- What
- Rolling stock maintenance, overhaul and spares
- Supplier
- Tidyco Limited
- Value
- £700,000
- How it was bought
- Direct award
- Dates and next
- Dec 2026 to Nov 2027
- Option to Nov 2028