Audleys Resource Centre changing room alterations go to Tew Brothers
- Hampshire County Council
- South East
- Call-off
- 15 October 2026 to 30 October 2026
Hampshire County Council had Tew Brothers Limited alter a toilet at Audleys Resource Centre so that a douche shower could be used with it.
The job set a shower into a dropped section of floor beneath the toilet pan. That meant reworking part of the underfloor heating under the chipboard floor and fitting a new water heater for the shower. The toilet end of the room got acrylic cladding on the walls and a vinyl floor, and the rest of the room was redecorated.
Tew Brothers, a small business, took the £23,030 order through the council's Minor Works Framework 2026-2030 in September 2026. The work was due to end in October 2026.
- What
- Toilet and washroom refurbishment
- Supplier
- Tew Brothers Limited
- Value
- £23,030
- How it was bought
- Call-off, Minor Works Framework 2026-2030
- Dates and next
- Oct 2026 to Oct 2026