Headland Cycleway in Hartlepool will be built by BCE Northern
- Hartlepool Borough Council
- North East
- Below threshold - limited competition
- 16 November 2026 to 16 August 2027
Hartlepool Borough Council has chosen BCE Northern to build the Headland Cycleway, a cycle link between the town centre and the Headland. The route is a joint scheme of TVCA and the council.
BCE Northern Limited, a small business, will lay a new tarmac track. Kerb lines, the carriageway and paving layouts will also be altered.
The council awarded the £3m contract in November 2026 after a limited competition. The works are due to finish in August 2027.
Contract ends August 2027
- What
- Footways, cycleways and path construction
- Supplier
- BCE Northern Limited
- Value
- £3m
- How it was bought
- Below threshold - limited competition
- Dates and next
- Nov 2026 to Aug 2027