Museum of Hartlepool conservation plan goes to Spencer & Fry
- Hartlepool Borough Council
- North East
- Open
- 1 November 2025 to 1 April 2026
Hartlepool Borough Council hired Spencer & Fry Limited to draw up a conservation management plan for the Museum of Hartlepool's collections. The plan belonged to the development phase of Tides of Change, the council's project to revitalise the museum and PS Wingfield Castle.
The collections run from archaeology and maritime material to working exhibits, textiles and art. The National Lottery Heritage Fund backed the project, and the plan had to follow the fund's good practice guidance on conservation planning.
Bids were scored 70% on quality and 30% on price in an open tender. The £15,000 contract ran from November 2025 and was due to end in April 2026.
- What
- Collections conservation and restoration
- Supplier
- Spencer & Fry Limited
- Value
- £15,000
- How it was bought
- Open
- Dates and next
- Nov 2025 to Apr 2026