High House Crossroads signals for Herefordshire Council go to Telent
- Herefordshire Council
- West Midlands
- Below threshold - award under framework
- 4 January 2027 to 4 April 2027
Herefordshire Council has hired Telent for traffic signal works at the High House Crossroads. The project covers that one junction, and the council placed the order under a framework agreement.
The £43,656 contract was awarded in October 2026. Telent's work is planned to take three months and is due to finish in April 2027.
Contract ends April 2027
- What
- Traffic signals and intelligent transport systems
- Supplier
- Telent
- Value
- £43,656
- How it was bought
- Below threshold - award under framework
- Dates and next
- Jan 2027 to Apr 2027