Weobley High School modular build for Herefordshire goes to S C Joseph
- Herefordshire Council
- West Midlands
- Below threshold - open competition
- 22 July 2026 to 22 July 2027
Herefordshire Council has hired S C Joseph Ltd to move a two-storey modular building from Peterchurch Primary School to Weobley High School.
The building is taken down at Peterchurch, carried to Weobley and put back up on new foundations. Its interior is remodelled and it is connected to services and drainage. The school's current single-storey mobile building also comes out. The council expected the works to take 4 to 6 weeks.
Bids in the open tender were scored 48% on quality, 12% on social value and 40% on price. The £235,585 contract runs from July 2026 to July 2027.
Contract ends July 2027
- What
- Modular and portable buildings
- Supplier
- S C Joseph Ltd
- Value
- £235,585
- How it was bought
- Below threshold - open competition
- Dates and next
- Jul 2026 to Jul 2027