Vacuum plant renewal for Hillingdon Hospitals goes to SHJ
- The Hillingdon Hospitals NHS Foundation Trust
- London
- Call-off from a framework agreement
- 4 March 2026 to 3 March 2027
The Hillingdon Hospitals NHS Foundation Trust has hired SHJ Hospital Pipelines Ltd to renew air compressor, vacuum and manifold plant. The work replaces existing equipment, which is part of the trust's medical gas pipeline systems.
The trust ordered the work through a framework agreement in March 2026. The £119,275 contract runs for 12 months, to March 2027.
Contract ends March 2027
- What
- Medical gas pipeline systems
- Supplier
- SHJ Hospital Pipelines Ltd
- Value
- £119,275
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Mar 2026 to Mar 2027