Macai completes boarding, drylining and finishes at Meadow-Royal Lane
- London Borough of Hillingdon
- London
- Direct
- 14 April 2025 to 29 August 2025
The London Borough of Hillingdon awarded Macai - Limited the boarding, drylining and finishes work on a part-built two-storey block at Meadow-Royal Lane.
ISG Construction Limited was given the contract to build the block in October 2023, with completion due in December 2024. ISG's trading companies went into administration in late 2024. To finish the project by September 2025, the council made direct awards to ISG's former sub-contractors.
Macai's £453,800 package was due to end in August 2025.
- What
- Plastering, dry lining and rendering
- Supplier
- Macai - Limited
- Value
- £453,800
- How it was bought
- Direct
- Dates and next
- Apr 2025 to Aug 2025