Newcastle Government Hub fit-out for HMRC goes to Bowmer & Kirkland
- HM Revenue & Customs
- North East
- Call-off from a framework agreement
- 24 January 2025 to 1 October 2027
HM Revenue & Customs (HMRC) hired Bowmer & Kirkland Ltd to design and fit out the Newcastle Government Hub at Pilgrim Quarter.
The firm started under a pre-construction services agreement for the Cat B works, after HMRC accepted its first-stage tender. HMRC may then issue a notice to proceed, appointing it to carry out the works under a JCT Design and Build Contract 2024.
HMRC ordered the work through a framework. The contract is worth £95,993,233 and runs to October 2027.
Contract ends October 2027
- What
- Interior fit-out and office reconfiguration
- Buyer
- HM Revenue & Customs
- Supplier
- Bowmer & Kirkland Ltd
- Value
- £96m
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Jan 2025 to Oct 2027