Sheppey school demolition: Homes England plans to clear Halfway House site
- Homes England
- South East
- 4 January 2027 to 30 April 2027
Homes England plans to hire a contractor to demolish the former Halfway House Primary School in Minster-On-Sea, on the Isle of Sheppey. The goal is a cleared site that Homes England can redevelop.
Buildings B1 to B7, B9 and B10 would come down to their ground floor slabs. The contractor would also strip out the buildings, remove asbestos with independent checks, and sort and recycle the waste. Bat mitigation measures apply, and dust, noise and vibration must be controlled.
The works would use the NEC3 Engineering and Construction Contract (Option A). A Prior Approval application was still with the local planning authority when the documents were drawn up, and the contractor must meet any conditions it brings. The estimate is £1m, and the works are due to run from January to April 2027.
- What
- Demolition and soft strip
- Buyer
- Homes England
- Estimated value
- £1m
- How it will be bought
- Not published
- Responses due
- 27 Aug 2026
- Contract dates
- Jan 2027 to Apr 2027