Contract awardedCarpentry and joinery
Karma Electrical & Fire Systems replaces door closers at Penfold Court
- Housing 21
- West Midlands
- Limited
- 2 March 2026 to 20 March 2026
Housing 21 hired Karma Electrical & Fire Systems to replace the door closers at Penfold Court with solenoid-activated units.
The work meant taking the old closers out, then fitting, wiring and commissioning the new ones. The aim was to meet fire safety and building access requirements.
The £76,428 job was due to be finished in March 2026.
- What
- Carpentry and joinery
- Buyer
- Housing 21
- Supplier
- Karma Electrical & Fire Systems
- Value
- £76,428
- How it was bought
- Limited
- Dates and next
- Mar 2026 to Mar 2026