Inner City Environmental repairs fire protection at Charing Cross Hospital
- Imperial College Healthcare NHS Trust
- London
- Below threshold - without competition
- 24 September 2026 to 31 March 2027
Inner City Environmental is carrying out passive fire protection work at Charing Cross Hospital for Imperial College Healthcare NHS Trust.
The work is part of the hospital's Water Mist Fire Protection System project. Shortcomings in fire protection had been found in the tower block's lift and stairwell core, and the contractor is putting them right. It also takes on extra work needed to keep the building compliant with fire safety rules.
The trust awarded the £1.7m contract directly, without a competition, in September 2026. It is due to end in March 2027.
Contract ends March 2027
- What
- Fire stopping, compartmentation and passive fire protection
- Supplier
- Inner City Environmental
- Value
- £1.72m
- How it was bought
- Below threshold - without competition
- Dates and next
- Sep 2026 to Mar 2027