Haylands Primary School gets replacement boilers from Wight Heating
- Isle of Wight Council
- South East
- Below threshold - without competition
- 24 July 2026 to 31 August 2026
Isle of Wight Council had new boilers, flues and pumps fitted at Haylands Primary School after the old equipment failed. The replacement was meant to restore the school's heating and hot water.
Wight Heating Ltd did the work. The council awarded it directly, with no competition. The £26,486 contract ran from July 2026 and was due to end in August 2026.
- What
- Commercial boilers and heating plant
- Supplier
- Wight Heating Ltd
- Value
- £26,486
- How it was bought
- Below threshold - without competition
- Dates and next
- Jul 2026 to Aug 2026