Imperial War Museums hired Lagan Airport Maintenance Limited to repair and resurface the hard runway at IWM Duxford.
The contract also covered the operational readiness platform, whose joints were to be cut away and repaired. Both jobs were needed so the surfaces stayed safe for continued use.
IWM awarded the £550,836 contract directly, without a competition, in June 2026. The work was due to end in September 2026.
- What
- Airfield pavements, runways and ground lighting
- Buyer
- Imperial War Museums
- Value
- £550,836
- How it was bought
- Below threshold - without competition
- Dates and next