Contract awardedCycle hangars and secure cycle parking

Building 30 bike shelters at the John Innes Centre go to Holmes

  • John Innes Centre
  • East of England
  • Below threshold - without competition
  • 2 October 2026 to 30 November 2026

The John Innes Centre has hired Holmes Building Contractors to build a new cycle compound with shelters at its Building 30.

The work covers a wall-mounted shelter for 18 bikes and two Dudley shelters for another 20, with a new retaining wall, a concrete slab and a painted fire escape route through the compound.

The centre awarded the £37,958 contract directly, without a competition, in October 2026. The work is due to end in November 2026.

Alert me to similar tenders

Contract ends November 2026

What
Cycle hangars and secure cycle parking
Value
£37,958
How it was bought
Below threshold - without competition
Dates and next
Oct 2026 to Nov 2026

How it was bought

1 official notice
  1. 2 Oct 2026Contract starts
  2. 9 Nov 2026Award noticeFind a Tender
  3. 30 Nov 2026Contract ends

How it compares

With every cycle hangars and secure cycle parking award since 2021

Half of awards fall between £31,293 and £187,900Median £56,979

Awards
91
Firms that won them
26
Median award
£56,979
of 87 with a value
This award
Smaller than 68%
of them
Typical length
1 year
In East of England
3 awards

Holmes Building Contractors ranks 10th of 26 firms for cycle hangars and secure cycle parking awards since 2021.

RankFirmAwardsValue
1Locked31£13.7m
2Locked24£1.59m
3Locked5£1.28m
4Locked3£3.9m
4Locked3£503,160
4Locked3£501,862
10Holmes Building Contractors Won this one1£37,958
See who wins this work

Figures to 21 November 2026

Cycle hangars and secure cycle parking at other buyers

John Innes Centre has awarded 27 contracts since 2021.

See John Innes Centre's page
  • Holmes Building Contractors has won 2 public contracts since 2021.