The John Innes Centre hired MJS Group to demolish existing buildings and renew roads and underground services across its site at Norwich Research Park. The work was part of the Next Generation Infrastructure (NGI) Programme, set up to develop facilities for the centre and The Sainsbury Laboratory and tackle their deteriorating infrastructure.
The contract covered an upgraded southern access road, new district heating pipework, surface water drainage, upgraded mains water, and new or moved communications and power cables. MJS Group was also to design the heating pipework, the reinforcement of retaining walls and the temporary works. The works sat on a live research site, next to healthcare buildings.
The centre awarded the £9.3m contract directly. It started in September 2025 and was due to end in November 2026. Turner & Townsend was named contract administrator and AECOM quantity surveyor.
- What
- Groundworks, enabling works and site infrastructure
- Buyer
- John Innes Centre
- Supplier
- MJS Group
- Value
- £9.3m