Churchill Centre boiler and distribution boards replaced by BSW
- Kent Community Health NHS Foundation Trust
- South East
- Open, 9 bids
- 18 February 2026 to 31 March 2026
Kent Community Health NHS Foundation Trust hired BSW Building Services to replace distribution boards and carry out boiler works at the Churchill Centre.
The centre is in the Royal British Legion Village at Preston Hall, Aylesford. Bidders needed Construction Silver Level accreditation with verified status. Installers had to hold BS7671 IET 18th Edition certification and be on the F-Gas Register for the gas boiler work.
The trust had estimated the works at £150,000. Nine bids came in to an open tender scored 70% on finance, 20% on quality and technical and 10% on sustainability and social value. BSW's award came to £218,344, nearly one and a half times the estimate, and the works were due to finish by March 2026.
- What
- Combined M&E building services installation
- Supplier
- BSW Building Services
- Value
- £218,344
- How it was bought
- Open
- 9 bids
- Dates and next
- Feb 2026 to Mar 2026