Contract awardedBuilding refurbishment, remodelling and conversion

St George's Guildhall refurbishment goes to Messenger Construction

King's Lynn and West Norfolk Borough Council awarded Messenger Construction £20.3m to refurbish St George's Guildhall, almost one and a half times the £14m estimate. Two bids came in through a restricted tender.

No larger medieval guildhall survives in the UK, and the building has hosted performances in every century since the 1400s. The council is redeveloping the site with the National Trust and Norfolk Museums Service. A charity, St George's Guildhall and Creative Hub CIO, will run it afterwards.

The work covers the listed guildhall and the conversion of historic barns into creative hubs, from foundations and structural steel to stage engineering and asbestos removal. Messenger Construction also acts as principal designer on a design taken to RIBA Stage 4. The contract runs from November 2025 to June 2028.

Alert me to similar tenders

Contract ends June 2028

What
Building refurbishment, remodelling and conversion
Value
£20.3m
How it was bought
Restricted procedure
2 bids
Dates and next
Nov 2025 to Jun 2028

How it was bought

4 official notices
  1. 19 Aug 2024Planning noticeDelta eSourcing
  2. 11 Oct 2024Tender noticeDelta eSourcing
  3. 11 Nov 2024Bids closed2 bids
  4. 18 Nov 2025Award noticeDelta eSourcing
  5. 18 Nov 2025Award noticeDelta eSourcing
  6. 24 Nov 2025Contract starts
  7. 30 Jun 2028Contract ends

King's Lynn and West Norfolk Borough Council has bought this 3 times since 2021

Last bought
Sep 2026
Typical length
10 months
Typical value
£1.29m
Suppliers used
3
AwardedContractWon byValue
Sep 2026Locked10 monthsLocked£1.29m
Jan 2026Locked6 monthsLocked£233,788
Oct 2025This purchase2.5 yearsMessenger Construction£20.3m

Suppliers King's Lynn and West Norfolk Borough Council has used

SupplierContractsValue
Messenger Construction Won this one1£20.3m
Locked1£1.29m
Locked1£233,788
See the contracts and who won them

Figures to 21 November 2026

How it compares

With every building refurbishment, remodelling and conversion award since 2021

Half of awards fall between £122,812 and £1.3mMedian £369,284

Awards
2,423
Firms that won them
1,114
Median award
£369,284
of 2,267 with a value
This award
Bigger than 98%
of them
Typical length
4 months
In East of England
175 awards

Messenger Construction ranks 241st of 1,114 firms for building refurbishment, remodelling and conversion awards since 2021.

RankFirmAwardsValue
1Locked34£32.1m
2Locked22£201.4m
3Locked20£38.7m
4Locked19£291.2m
4Locked19£67.2m
4Locked19£948,867
241Messenger Construction Won this one2£25.4m
See who wins this work

Building refurbishment, remodelling and conversion at other buyers

King's Lynn and West Norfolk Borough Council has awarded 228 contracts since 2021.

See King's Lynn and West Norfolk Borough Council's page
  • Messenger Construction has won 6 public contracts since 2021.

26 building refurbishment, remodelling and conversion tenders are open now

See them
More building refurbishment, remodelling and conversion contracts awarded in 2025