Crosby Granger and John Coward assess Lake District farm buildings
- Lake District National Park Authority
- North West
- Open, 19 bids
- 30 October 2025 to 20 March 2026
Lake District National Park Authority awarded £100,500 for feasibility studies on traditional farm buildings, about two-thirds of its £150,000 estimate.
The authority wanted specialists in Lake District vernacular buildings to plan repairs that would keep the buildings in farm use. Each study needed a short history of the building, a structural engineer's survey and an ecologist's habitat survey. Repairs had to be graded urgent, necessary or desirable and set out in a schedule of works, priced by a quantity surveyor, for a future tender.
The five lots drew 19 bids. Price counted for 40% of the score, quality for 49% and social, economic and environmental value for 11%. Crosby Granger Architects won lots 1 to 4, and John Coward Architects was also appointed. The contract ran from October 2025 and was due to end in March 2026.
- What
- Conservation and heritage architecture
- 4 of 5 lots awarded
- Value
- £100,500
- Across 4 lots
- How it was bought
- Open
- 19 bids
- Dates and next
- Oct 2025 to Mar 2026