Hoverdale removes the percolators at Thornton for Lancashire Renewables
- Lancashire Renewables Limited
- North West
- Below threshold - unknown
- 10 August 2026 to 18 December 2026
Lancashire Renewables Limited hired Hoverdale UK Limited to take out the percolators in the processing buildings at Thornton.
Hoverdale's job covers more than the units themselves. The platforms, ducting, pipework and steelwork linked to them also come out, and the electrical connections are taken off. The work has to be done safely and fitted around the site's own operations.
The £339,000 contract started in August 2026 and is due to end in December 2026.
Contract ends December 2026
- What
- Demolition and soft strip
- Supplier
- Hoverdale UK Limited
- Value
- £339,000
- How it was bought
- Below threshold - unknown
- Dates and next
- Aug 2026 to Dec 2026