Mavisbank House rescue: LDN Architects leads the design team
- The Landmark Trust
- Scotland
- Restricted procedure, 5 bids
- 1 November 2024 to 1 January 2031
The Landmark Trust appointed LDN Architects as the design team for the conservation of Mavisbank House and its pavilions.
The first phase, Rescue, covers RIBA Stages 2 and 3 and the planning and other consent applications. If the land is secured and planning granted, the team takes the works through RIBA Stages 4 to 7. A second phase, Restore, is an option for the trust, tied to funding applications to the NLHF. The lead architect had to be an accredited conservation architect with experience of Grade I or Grade II* buildings.
Five bids came in. Experience and team each counted for 20% of the score, key issues and method and programme 15% each, and price 30%. The £269,368 award was below the £380,000 estimate, and the contract runs to January 2031.
Contract ends January 2031
- What
- Conservation and heritage architecture
- 2 of 2 lots awarded
- Buyer
- The Landmark Trust
- Supplier
- LDN Architects
- Value
- £269,368
- Across 2 lots
- How it was bought
- Restricted procedure
- 5 bids
- Dates and next
- Nov 2024 to Jan 2031