Mersey Tidal Power Project consenting support comes from WSP
- Liverpool City Region Combined Authority
- North West
- Limited
- 13 November 2025 to 13 May 2026
WSP gave Liverpool City Region Combined Authority interim consenting and environmental impact assessment support on the Mersey Tidal Power Project (MTPP).
The contract kept the project moving in the gap between consenting management contracts. The previous one ended in June 2025, and its replacement was still out to tender. The Evidence Plan process, flagged as time critical, was part of the work.
The authority awarded the £149,994 contract directly. It ran from November 2025 and was due to end in May 2026.
- What
- Planning consultancy for applications and appeals
- Supplier
- WSP
- Value
- £149,994
- How it was bought
- Limited
- Dates and next
- Nov 2025 to May 2026