Liverpool City Region Combined Authority has hired WSP to test the case for new rail stations at Woodchurch in Wirral and Daresbury in Halton.
WSP will gauge current and future passenger demand at each site, explore design options and price them at a high level. The work feeds the authority's Gateway 1 and Gateway 2 stages, ending with a Gateway 2 business case built on the DfT's five-case model.
The authority chose WSP after a limited competition in September 2026, at £68,903. The work runs to March 2027.
Contract ends March 2027
- What
- Transport modelling and scheme appraisal
- Supplier
- WSP
- Value
- £68,903
- How it was bought
- Below threshold - limited competition
- Dates and next
- Sep 2026 to Mar 2027