BT moves its assets clear of the A511 Growth Corridor works
- Leicestershire County Council
- East Midlands
- Direct
- 20 April 2026 to 1 May 2027
Leicestershire County Council is paying BT to divert telecoms assets that sit in the path of the A511 Growth Corridor Programme.
The programme is moving towards Stage 2 construction. A number of BT assets sit where junctions are to be realigned, the road widened and other civil engineering done. They must move before full works can start. As the owner of the assets, BT was the only supplier that could do the work.
The council awarded the £1.75m contract directly in April 2026. It runs to May 2027.
Contract ends May 2027
- What
- Telecoms duct and diversion civils
- Supplier
- BT
- Value
- £1.75m
- How it was bought
- Direct
- Dates and next
- Apr 2026 to May 2027