300 EV column chargers for Liverpool come from Otaski Energy Solutions
- Liverpool City Council
- North West
- Open, 4 bids
- 10 December 2025 to 9 December 2035
Liverpool City Council hired Otaski Energy Solutions Ltd as the charge point operator for 300 electric vehicle (EV) column chargers. Otaski puts in the chargers, then runs and maintains them for up to 12 years. It also buys the electricity and charges users for it per kWh.
Four bids came in, scored 50% on quality, 40% on price and 10% on social value. The £12m contract runs to December 2035, or to December 2037 if its two-year extension is taken.
Contract ends December 2035
- What
- Public EV charging network concessions
- Supplier
- Otaski Energy Solutions Ltd
- Value
- £12m
- How it was bought
- Open
- 4 bids
- Dates and next
- Dec 2025 to Dec 2035