Berth 5 container yard at London Gateway goes to Gobion Construction
- London Gateway Port Limited
- London
- Selective
- 31 March 2026 to 30 March 2027
London Gateway Port Limited hired Gobion Construction Ltd to build the container storage yard at Berth 5 of London Gateway Port. The work covers 10 automated stacking crane (ASC) modules.
Gobion designs and builds the electrical works, including 11kV power to the cranes and reefers, the substations and SCADA systems for control and monitoring. The civil works follow the port's own design: heavy-duty pavements on ground prepared using high energy impact compaction, plus crane rails, drainage, water mains and lighting towers.
The restricted tender weighted the commercial bid at 60% and the technical bid at 40%. Gobion was awarded £52.3m in March 2026, against a £60m estimate, and the contract runs to March 2027.
Contract ends March 2027
- What
- Harbour, marine and mooring works
- Supplier
- Gobion Construction Ltd
- Value
- £52.3m
- How it was bought
- Selective
- Dates and next
- Mar 2026 to Mar 2027