Leeds Conservatoire lift design for Luminate goes to Currie & Brown
- Luminate Education Group
- Yorkshire and the Humber
- Call-off
- 2 October 2025 to 1 August 2026
Luminate Education Group appointed Currie & Brown to design and specify a new lift for Leeds Conservatoire.
The first stage took the design and specification to RIBA Stage 4. A second stage depended on funding being available. In it, Currie & Brown would take the design on to RIBA Stage 5. The firm would also project manage buying and fitting the lift, with the building, mechanical and electrical work around it.
Luminate awarded the £72,675 contract directly through NHS SBS's Construction Consultancy Services 3 framework (SBS10190). The work began in October 2025 and was due to end in August 2026.
- What
- Lift and vertical transportation consultancy
- Supplier
- Currie & Brown
- Value
- £72,675
- How it was bought
- Call-off, Healthcare Planning, Construction Consultancy and Ancillary Services (HPCCAS)
- Dates and next
- Oct 2025 to Aug 2026