Keystream supplies a project manager for MCA's Aberdeen data centre move
- Maritime and Coastguard Agency
- Scotland
- Call-off from a framework agreement
- 24 November 2025 to 18 May 2026
The Maritime and Coastguard Agency hired a Keystream Group project manager to oversee its Aberdeen data centre move and decommissioning. The role covered the technical side of moving data centre infrastructure, project governance and stakeholder management, through to closing the old facility.
Keystream Group, a small business, was taken on through a call-off from a framework agreement. The six-month contract was worth £84,700. It ran from November 2025 and was due to end in May 2026.
- What
- IT programme and project management
- Supplier
- Keystream Group
- Value
- £84,700
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Nov 2025 to May 2026