Cannizaro toilet block refurbishment goes to Taylor Building Company
- London Borough of Merton
- London
- Open procedure
- 28 August 2026 to 28 January 2027
The London Borough of Merton is paying Taylor Building Company Ltd to refurbish the Cannizaro toilet block.
Inside the male, female and disabled toilets, the contractor is repainting, renewing basins, taps and toilet fittings, and laying a resin floor in the cubicles. It is also adding hot water, replacing the frost-protection heaters and repairing the brickwork and roof.
Taylor Building was chosen after an open tender. The £35,000 contract started in August 2026 and is due to end in January 2027.
Contract ends January 2027
- What
- Toilet and washroom refurbishment
- Supplier
- Taylor Building Company Ltd
- Value
- £35,000
- How it was bought
- Open procedure
- Dates and next
- Aug 2026 to Jan 2027