Legionella works in MHRA laboratories go to Parker Air Conditioning
- Medicines and Healthcare products Regulatory Agency (MHRA)
- East of England
- Call-off from a framework agreement
- 12 January 2026 to 31 March 2026
The Medicines and Healthcare products Regulatory Agency (MHRA) hired Parker Air Conditioning for legionella remedial works in its laboratories and riser cupboards.
A survey logged problems wherever it could reach behind cabinets and benches, but some areas were restricted. The agency allowed a sum to cover rooms that could not be entered. The works included descaling outlets and putting right dead legs, with contingency sums for issues found as the work went on. The survey also suggested a circulating pump to raise the low hot water temperature.
Some of the work needed a full shutdown of the North or South block, so it would need to happen out of hours, with weekend working suggested. MHRA ordered the works through a framework for £24,000, and the contract was due to end in March 2026.
- What
- Water hygiene and Legionella control
- Supplier
- Parker Air Conditioning
- Value
- £24,000
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Jan 2026 to Mar 2026