Contract awardedHeat pumps
NIBE heat pumps for MHS Homes Group are fitted by Stonegrove
- MHS Homes Group
- South East
- Direct
- 9 January 2026 to 31 July 2026
MHS Homes Group hired Stonegrove Limited to install NIBE air source heat pumps in residential properties. The work covered fitting the units and commissioning them. Stonegrove is a small business.
The group awarded the £33,435 contract directly, without a tender. The seven-month job started in January 2026 and was due to finish in July 2026.
- What
- Heat pumps
- Buyer
- MHS Homes Group
- Supplier
- Stonegrove Limited
- Value
- £33,435
- How it was bought
- Direct
- Dates and next
- Jan 2026 to Jul 2026