i4C Innovation & Cleantech Centre build planned by Mid and East Antrim
- Mid and east Antrim Borough Council
- Northern Ireland
- 1 February 2028 to 31 December 2029
Mid and East Antrim Borough Council plans to build the i4C Innovation & Cleantech Centre in Ballymena. The centre would serve businesses in clean technology, innovation and advanced manufacturing. Plans include light industrial workshops alongside offices and space for collaboration and innovation, plus parking and landscaping.
Before it goes to tender, the council asked contractors for views on programme length, buildability, supply-chain lead times and risk. It also asked for feedback on its proposed BREEAM objectives and on social value. The council is still weighing whether loose furniture belongs in the construction contract.
The construction contract is estimated at about £20m, including allowances for risk and inflation. Work is expected to run from February 2028 to December 2029.
- What
- New-build construction of non-residential buildings
- Estimated value
- £20m
- How it will be bought
- Not published
- Responses due
- 16 Nov 2026
- Contract dates
- Feb 2028 to Dec 2029