Charities Hub's parapet wall gets a rebuild from Gaskell Refurbishments
- Milton Keynes City Council
- South East
- Below threshold - open competition
- 7 September 2026 to 20 November 2026
Milton Keynes City Council hired Gaskell Refurbishments Ltd to rebuild the first-floor parapet wall at the Charities Hub in Galley Hill.
The hub, home to the Arts Centre and Meeting Place, dates from the early 1970s and sits in a steel-framed local centre with shops. Gaskell rebuilds the wall to the approved drawings and adds flashing and a gutter at its base to stop water pooling, once Building Control has approved the work.
Price carried 60% of the score and quality 40%. The £109,961 contract runs from September 2026 and is due to end in November 2026.
- What
- Brickwork and masonry repairs
- Supplier
- Gaskell Refurbishments Ltd
- Value
- £109,961
- How it was bought
- Below threshold - open competition
- Dates and next
- Sep 2026 to Nov 2026