Baily Garner manages The Hide & Fullers Slade works for Milton Keynes
- Milton Keynes City Council, run by Prosper
- South East
- Call-off
- 4 September 2026 to 29 September 2028
Milton Keynes City Council has brought in Baily Garner to project manage the capital works at The Hide and Fullers Slade. The consultant also gives wider consultancy support on The Hide and Fullers Capital Works.
Prosper ran the purchase for the council, a direct award under its Design & Consultancy Services Framework - National. Baily Garner, a small business, takes the £205,000 contract from September 2026 to September 2028.
Contract ends September 2028
- What
- Construction project management
- Supplier
- Baily Garner
- Value
- £205,000
- How it was bought
- Call-off, PROSPER
- Dates and next
- Sep 2026 to Sep 2028