Arcadis supervises Frongoch culvert works for Mining Remediation Authority
- Mining Remediation Authority
- Wales
- Call-off from a framework agreement
- 30 January 2026 to 31 July 2026
Arcadis provided project management and site supervision for the Mining Remediation Authority's culvert flow gauging works at Frongoch.
The construction contract itself had been let separately after an open tender, under the NEC4 Engineering and Construction Contract Main Option A. Arcadis was to act as the NEC project manager and supervise the site. The onsite works were expected to take six weeks.
The £31,478 contract started in January 2026 and was due to end in July 2026.
- What
- Construction project management
- Supplier
- Arcadis
- Value
- £31,478
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Jan 2026 to Jul 2026