Mine water assessments for Mining Remediation Authority go to AECOM
- Mining Remediation Authority
- Call-off
- 9 March 2026 to 8 March 2033
The Mining Remediation Authority hired AECOM to assess mine water risk across the blocks of its Inland Saline Mine Water Programme (ISMWP).
The programme's 'Block to Scheme' process decides what treatment each block needs. AECOM covers three of its steps. It works out where and when mine water might discharge from each block, and how fast it is rising. It checks whether nearby watercourses can take the discharges. Then it ranks the blocks by risk, judged on the volume and quality of mine water reaching watercourses or aquifers, and the timing.
The authority ordered the work through Management Consultancy Framework Four (RM6309) in March 2026. The contract runs five years, with an optional two more to March 2033. The £8.3m value is an estimate covering all seven years, with an allowance for inflation.
Contract ends March 2033
- What
- Catchment management and water environment assessment
- Supplier
- AECOM
- Value
- £8.32m
- How it was bought
- Call-off, MCF4
- Dates and next
- Mar 2026 to Mar 2033