Sharnberry MWTS power line is rebuilt by Northern Powergrid
- Mining Remediation Authority
- North East
- Direct
- 20 February 2026 to 31 December 2026
The Mining Remediation Authority is paying Northern Powergrid to extend the grid to a mine water treatment scheme at the former Sharnberry mines. Environment Agency monitoring found the Sharnberry adit was the main source of zinc and cadmium in the Euden Beck and Bedburn Beck. The scheme needs a permanent power supply.
Phase 1 covers the stretch from Eggleston Crest to the edge of the Eggleston Estate access track. Phase 2 is the work only the network operator can do. Northern Powergrid is taking on the Senior Authorised Person work for the connections, rebuilding the two-conductor line as three-phase and making one high-voltage closing joint.
The authority awarded the £435,072 contract directly. It runs to December 2026, and can be extended to December 2027 if site conditions or weather delay the work.
Contract ends December 2026
- What
- Electricity network works and connections
- Supplier
- Northern Powergrid
- Value
- £435,072
- How it was bought
- Direct
- Dates and next
- Feb 2026 to Dec 2026
- Option to Dec 2027