GW Power Safe develops solar PV schemes for Mining Remediation Authority
- Mining Remediation Authority
- Below threshold - unknown
- 24 August 2026 to 23 August 2028
The Mining Remediation Authority wants to add to its solar installations and build a pipeline of schemes for the coming years. GW Power Safe, a small business, is doing the development work that will take those schemes forward.
The work sets out design and construction costs, expected energy generation and the savings that follow. It also covers full costings for the PV systems, enabling works and site infrastructure. The aim is to bring schemes to the point where the authority can make accurate investment decisions and show value for money.
The £167,456 contract runs for two years from August 2026.
Contract ends August 2028
- What
- Local area energy planning and energy infrastructure feasibility
- Supplier
- GW Power Safe Ltd
- Value
- £167,456
- How it was bought
- Below threshold - unknown
- Dates and next
- Aug 2026 to Aug 2028