Wilo supplies a new shaft pump for Wheal Jane Mine Water Treatment Plant
- Mining Remediation Authority
- South West
- Below threshold - limited competition
- 10 March 2026 to 30 June 2026
The Mining Remediation Authority bought a new shaft pump from Wilo (U.K.) Ltd for Wheal Jane Mine Water Treatment Plant. The 55 kW unit replaced the pump in use there. The order also covered 6-inch Wellmaster hoses for the pump and 80 metres of four-core 35mm cable.
The authority chose Wilo after a limited competition. The £47,524 contract started in March 2026 and could run to December 2026.
- What
- Pumping stations and small treatment plants
- Supplier
- Wilo (U.K.) Ltd
- Value
- £47,524
- How it was bought
- Below threshold - limited competition
- Dates and next
- Mar 2026 to Jun 2026
- Option to Dec 2026